PERIform Sverige, Projekt - Form, Ställning, Konstruktion - Luesslingen Tunnel, Solothurn, Switzerland PERIform Sverige, Projekt - Form, Ställning, Konstruktion - Luesslingen Tunnel, Solothurn, Switzerland PERIform Sverige, Projekt - Form, Ställning, Konstruktion - Luesslingen Tunnel, Solothurn, Switzerland Fler bilder  

Luesslingen Tunnel, Solothurn, Switzerland



First monolithically constructed tunnel in Switzerland

The 1,240 m long structure, with a road tunnel in each direction and a central service duct, was cast monolithically in 10 m sections. Base, walls and roof were poured in a single operation.

Advantage: The elimination of horizontal construction joints.

All of the shuttering operations, such as erection, adjustment, moving and striking, were fully hydraulic. The ACS 100 climbing mechanism, from PERI´s Automatic Climbing System, was used to move the guide beams. It proved possible to maintain the consortium´s stipulated weekly cycle right from the outset.

Contractor: Arge Lüt S88 Conti, Marti, Meier+Jäggi, Stuag
Field Service: PERI Germany, Weissenhorn, PERI Switzerland, Ohringen