PERIform Sverige, Projekt - Form, Ställning, Konstruktion - D''Areuse Motorway Tunnel, Switzerland PERIform Sverige, Projekt - Form, Ställning, Konstruktion - D''Areuse Motorway Tunnel, Switzerland PERIform Sverige, Projekt - Form, Ställning, Konstruktion - D''Areuse Motorway Tunnel, Switzerland Fler bilder  

D''Areuse Motorway Tunnel, Switzerland



Self-driving tunnel formwork adjusts hydraulically to the changing cross-section geometry

The construction of the A5 motorway between Neuchâtel and Yverdon includes a 481 m long tunnel near d´Areuse. A feature of the tunnel project is the variable cross-sections in both rectangular tunnels.

Originally planned as separate construction units (five working cycles), this type of construction was quickly discarded for the much faster semi-monolithic construction method (three working cycles) favoured by PERI. The reason for this: walls and slabs can be constructed in one pour.

The formwork carriages take less than one minute to travel the 12.00 m to the next concreting section. The whole process for striking, lowering, traveling, cleaning and repositioning could be carried out by a three-man crew in only one hour. Limited by specified striking times, zone section was finished every two weeks.

Contractors: F. Bernasconi & Cie SA. / S. Faccinetti SA.
Field Service: PERI Switzerland, Ohringen
PERI kontor: PERI AG, Switzerland