To meet the very tight schedule specified the tunnel was built monolithically in 10 m weekly cycles, ie base, walls and roof slab in a single pour with no joints.
|
|
The 1,240 m long structure, with a road tunnel and a central service duct, was cast monolithically in 10 m sections.
|
|
In the year 2000 the Øresund Project will link Denmark and Sweden with a four-lane motorway and double-track railway.
|
|
The construction work had to be finished by the start of the Skiing World Championship.
|
|
An inclined level of 30° formed the platform for the collar formwork. The falsework for this was of MULTIPROP towers and HD 200 heavy-duty props.
|