The PERI UP T 70 was erected as a working scaffold for the painter and a roof edge protection scaffold for the roofer to replace the asbestos tiles with a new copper roof.
|
|
Since the beginning of the nineties the annual number of air passengers has almost doubled to around 8 million in the capital of Baden-Wuerttemberg.��
|
|
The restoration of the masonry of the Old City Hall has been ongoing for the past two years and will continue for the next 2-3 years.
|
|
The site receives a scaffold, free of ballast and anchors, which can be moved and repositioned without modification.
|
|
PERI UP site stair towers can be erected without bracing as a stand alone tower or attached to the outside of a working scaffold to a height in excess of 90 m.
|